UCP’s ‘Wild West approach’ misses the mark on data centres, opposition says

UCP’s ‘Wild West approach’ misses the mark on data centres, opposition says

By George Lee, Local Journalism Initiative Reporter

The UCP government remains ill-prepared to deal with an onslaught of proposed new data centres that so far could require 20 gigawatts of power to run, the NDP said last week.

With Alberta the possible home for around 90 per cent of Canada’s anticipated power draw for major AI data centres, the government’s tack is all wrong, Opposition speakers said during the party’s public consultation in St. Albert.

The government is “going full tilt” on projects when it should have first spoken to affected communities, NDP Deputy Leader Rakhi Pancholi said in an audio recording her party provided to this reporter.

“We want to see what the economic development plan is,” said Pancholi, who represents Edmonton-Whitemud as an NDP MLA, in the first of three consultations put on by the party.

The second NDP consultation takes place today, Aug. 12, in Red Deer at 6:30 p.m., followed by an online event at 6 p.m. a week later.

Also happening Aug. 19, in Ponoka, is the first UCP town hall on the subject.

Last Thursday, the province announced it had launched an online information hub on AI data centres and will provide “comprehensive information” at a series of town halls.

The proposal rush
The advent of AI data centres in Alberta has been powering up rapidly since the UCP launched a strategy in early December 2024 to address the development of them.

Within days of the strategy’s publication came the announcement of Wonder Valley, a proposal for an AI industrial park in the Municipal District of Greenview near Grande Prairie, northwest of Edmonton.

Touted by proponent and celebrity entrepreneur Kevin “Mr. Wonderful” O’Leary, the controversial proposal would produce 7.5 to nine gigawatts of power, he speculated.

Today, at least 13 campuses for distinct, large-scale AI data centres are proposed in Alberta, according to data compiled from public disclosures by independent researchers.



Twenty gigawatts — the possible future requirement from Alberta centres dedicated to serving artificial intelligence — would run 15 million to 20 million average homes. The number closes in on Alberta’s installed capacity of 23.1 gigawatts at the end of 2024.

“This is not about saying yes or no to big projects,” Pancholi said during the Aug. 4 St. Albert event. “It’s about making sure we have the right framework in place so Albertans can be assured that they have a strong plan going forward, and that the things that they care about are also protected.”

Added Nathan Ip, the shadow minister of technology and innovation and the NDP member representing Edmonton-South West: “It’s clear that the Wild West approach the government is taking just isn’t working.”

But in an earlier interview with this reporter, Ip’s counterpart with the UCP said his government is acting on a thought-out plan.

Given more rushed examples set by approvers in other jurisdictions — many in the U.S. — Albertans have been “asking the right questions,” said Nate Glubish, the minister of technology and innovation.

“It’s been important to me to try and make sure that we validate the concerns that Albertans have, because they are rooted in real-world examples,” acknowledged Glubish, the UCP member for Strathcona-Sherwood Park.

“But then I highlight for Albertans that we chose not to be first in this industry. We wanted to be the smartest, so we spent two years developing a regulatory framework to protect their interests.”

He said a “bring-your-own-power” model means Alberta proposals won’t negatively affect the grid.

So far, the generation that proponents bring comes mostly from burning natural gas.

UCP meets the public on issue
First up for the UCP sessions on AI data centres is an in-person town halls in Ponoka on Aug 19 and Sturgeon County the next day.

A provincewide virtual town hall takes place a week later, on Aug. 27, followed by another in-person event in Grande Prairie.

All the UCP town halls begin at 6 p.m.

Last week’s NDP event was held about 50 kilometres away from the site of a controversial AI data centre being built by social media giant Meta in Sturgeon County.

The $13-billion project would feature nearly 270,000 square metres of data centre buildings on a 1,750-acre site.

The largest AI data centre in Canada so far, Meta’s project would incorporate closed-loop cooling. “It acts like a car radiator. It’s the same fluid in and out the whole time, for the entire life of the facility,” said Glubish.

Meta’s facility will use less water than an average golf course, he claimed, calling it “a testament to (the company’s) modern, state-of-the-art, best-in-class technology to run this data centre so that they can minimize their impact on the environment.”

He continued: “That’s what we want to see when we talk about large-scale data centres coming to Alberta.”



But at the St. Albert event the NDP drew attention to a delay between Meta’s full startup in roughly three years at around one gigawatt and actual generation of its own power a year or so later.

The centre is expected to start drawing heavily from the grid sometime in 2028.

Said Ip: “I think there are questions about what are the safeguards in place to ensure that the increases won’t be passed on to ratepayers, and I don’t think we have clear answers from government.”